Project Name : WG TASMAN Client/ Owner : SCHLUMBERGER( WESTERN GEECO) Year of Execution : 2009-2010

galvus met drugs.com Birkerød Description works done :

  • Fabrication and installation of platforms inside funnel – port & stbd.
  • Fabrication and installation of shell doors.
  • Fabrication and installation of bulwark doors & pilot platforms.
  • Modification of engine room ducts.
  • Fabrication and installation of engine room platforms.
  • Fabrication and installation of supports, LSA & FFA items.
  • Fabrication and installation water tight hatches.

Project Name : WG COOK Client/Owner : SCHLUMBERGER( WESTERN GEECO) Year of Execution : 2009-2010

ivermectin boehringer Description works done :

  • Fabrication and installation of platforms inside funnel – port & stbd.
  • Fabrication and installation of shell doors.
  • Fabrication and installation of bulwark doors & pilot platforms.
  • Modification of engine room ducts.
  • Fabrication and installation of engine room platforms.
  • Fabrication and installation of supports, LSA & FFA items.
  • Fabrication and installation foundations for Azimuth thrusters.

Project Name : FPSO FRADE Client/Owner : SBM IMODCO & CHEVRON Year of Execution : 2008-2009

https://al-hadeed-rollingshutter.in/27-cat/casino_10.html Description works done :

  • Fabrication and installation of platforms in pump room & engine room.
  • Fabrication and installation of sea water pump platforms in forepeak tanks.
  • Fabrication and installation of various foundations in engine room.
  • Relocation of purge pipes.
  • Fabrication and installation of fire monitor platforms.
  • Fabrication and installation of supports & gratings on turret from main deck level to top.

Project Name : FSO TI ASIA & TI AFRICA Client/Owner : EURONAV & OVER SEAS GROUP Year of Execution : 2010-2011

saganing casino Alapayevsk Description works done :

  • Fabrication and installation of platforms in pump room & engine room.
  • Fabrication and installation of accommodation light supports & supports.
  • Fabrication and installation of various foundations in engine room.
  • Fabrication and installation of metering skid platforms with gratings

Project Name : Emirates Flight Training Centre , Silicon Oasis Client/Owner : AMB Building Contracting llc Year of Execution : 2016

Loves Park ivermectin tablets for humans walmart Description works done :

  • Supply and  installation of all pipes and valves  including connecting to the compressor
  • Breathing air purifier and drain equipments including testing and commissioning of compressed air  system complete
  • Prefabrication and erection of platforms and handrails

Project Name : MAHARSHI VAMADEVA Client /owner : VARUN SHIPPING Year of Execution : 2012-2013

stromectol price dubai Sidoarjo Description works done :

  • Pipe line installation on main deck and pump room.
  • Fabrication and installation of pipe supports on main deck
  • New ac foundation on pump room
  • Fabrication, modification and installation of supports for electrical panels & cable trays on near accommodation areat

Project Name : FPSO OCEAN ( DEEP PRODUCER 1) Client/Owner : FRED OSLEN, Norway Year of Execution : 2009 - 2010

Castro Valley ivermectin injection for dog ticks Description works done :

  • Fabrication, modification and installation of supports for electrical panels & cable trays inside moon pool, thruster rooms & generator rooms

Project Name : FPSO GIMBOA Client/Owner : SAIPEM eni, ITALY Year of Execution : 2007 - 2008

Description works done :

  • Fabrication, modification and installation of engine room handrails from main deck level to engine room bottom

project Name : Al Dhaid Project Client/Owner: Hardco Building Contracting llc 3Year of Execution : 2016

project Name :  Al Dhaid Project

Client/Owner:  Hardco Building Contracting llc

3Year of Execution   :  2016